Hummer VI Sputter Coater

  1. Check:
    • Timer switch is on MANUAL and knob is at zero.
    • Gas switch is set to OFF .
    • Voltage switch is OFF .
  2. Open sample chamber.
  3. Place sample in chamber and close lid gently.
  4. Turn main power on and place slight pressure on lid to start vacuum seal.
  5. Set Mode switch to PLATE .
    • ( Note : Do not switch between modes when high-voltage is on. )
  6. Wait till pressure reaches ~50 mTorr and toggle gas switch to ON .
  7. Make sure gas is on and wait for pressure to stabilize. (~80 mTorr)
  8. Make sure voltage dial is set to zero, then turn voltage switch to ON .
    • ( Note: process starts when plasma is ignited (pink-purple glow) )
    • ( Note: if plasma flickering develops, check pressure and current )
  9. Turn voltage control knob clockwise to achieve approximately 30 milliamps.
  10. Let the machine run for 3 to 5 minutes.
  11. Turn voltage control knob to zero. Turn voltage switch OFF .
  12. Turn gas toggle switch to OFF .
  13. Turn main power switch to OFF , the system will automatically vent itself.
  14. When atmospheric pressure is reached in the sample chamber (lid will be loose), open lid and remove sample.